Novosibirsk | Ob River Crossing – Bugrinsky Bridge in Novosibirsk |
Sochi. | Back-up of Kurortny Prospect, 3 stage |
Voronezh Region, Rostov Region (reconstruction)
Design, detailed design, construction supervision
Project period: 2008 –
Present
General Designer: Institute Stroyproekt
Client: Russian Highways State Company
Description
The M-4 Don runs through Voronezh, Rostov-on-Don and Krasnodar and connects the central and northern regions of the European part of the country with the Northern Caucasus, the Black Sea coast, and the port of Novorossiysk. The road is part of the international North-South transport corridor.
Our company developed the design and detailed design for reconstruction of several road sections, including settlements bypasses.
Reconstruction of the motorway will improve the traffic and environmental situation, reduce travel time and ensure driving comfort for all road users.
Technical Parameters
Total length — 1589 km
Length of road sections designed/supervised by Stroyproekt — 454 km
Scope of Work
Section km 517 — km 544
Voronezh Region
Construction supervision
Section km 633 — km 715
Voronezh Region
Design and detailed design for construction
Section km 877 — km 907
Rostov Region
Design for construction
Section km 892 — km 907
Rostov Region
Detailed design for construction
Section km 933 — km 1024
Rostov Region
Design for rehabilitation
Section km 1024 — km 1091
Rostov Region
Design and detailed design for rehabilitation and construction
Section km 1091 — km 1119
Rostov Region
Design and detailed design for rehabilitation
Section km 1319 — km 1345
Krasnodar Region
Design and detailed design for rehabilitation and construction of interchanges
Far West Krasnodar Bypass
Design and detailed design for construction
Radiometric inspection system at the border of Rostov and Krasnodar Region
Pilot project of a radiometric inspection system for detection of illegal weaponry and dangerous goods, Kushchevsky district of Krasnodar region
|
25.12.2020
M-4 Don Section in Rostov Region opens after rehabilitation On 24 December, the M-4 Don highway section between 1024 km and 1036 km was opened after rehabilitation. Rehabilitation works started in spring 2019. |
| |
|
01.03.2018
Construction of Aksai Bypass Started on M-4 Don Highway in Rostov Region A groundbreaking ceremony that took place on 27 January 2018 signaled the start of construction of Aksai bypass, which will be part of the M-4 Don. |
| |
![]() |
19.01.2018
Preparatory Works Start on Aksai Eastern By-pass Road construction will start right after completion of preparatory works. The road route will run through Oktyabrsky, Aksaisky and Azovsky Districts and Novocherkassk and Bataisk. The total length of the road will be 65.5 km. |
| |
|
22.05.2017
M-4 road section opened to traffic in Rostov Region The opening ceremony took place on 19 May. The ceremony was attended by Vice-Speaker of the Council of the Federation Evgeny Bushmin, Minister of Transport Maxim Sokolov, Governor of Rostov Region Vasily Golubev, Chairman of the Avtodor Board Sergei Kelbakh and the top managers of the main design company – Aleksei Zhurbin, the General Director of Institute Stroyproekt and Alexander Kusik, the Director of Stroyproekt Rostov Office. |
| |
![]() |
21.03.2017
Expert review authority’s approval received for the radiometric control station project on the M-4 Don highway The positive opinion by the expert review authority was received for the design documentation, engineering survey results and cost estimates. |
|
![]() |
Far West Krasnodar Bypass Description A new 51km-long bypass road will run through three municipalities of Krasnodar Region and will have grade-separated interchanges with the existing railway and motor roads. The route will start at the junction with the federal highway M-4 Don and end at the junction with the federal highway A-289 between Krasnodar and the A-290 road Novorossiysk - Kerch. |
|