Approach Road to New Platov Airport

Rostov Region (new construction)
Working Documentation
Project period: 2017 – 2019
General Designer: AO Institute Stroyproekt
Contractor: AO Donaerodorstroy
Client: Ministry of Transport of Rostov Region


The new approach road links the new Platov airport with the northern by-pass of Rostov-on-Don and the M4 Don highway. Platov airport was built in 2017 as part of preparation for the 2018 FIFA World Cup.

Main Parameters

road length: 16 km
road category: 1B express road
design speed: 120 km/h
number of lanes: 4
carriageway width: 3.75 x 4 m
shoulder width: 3.75 m
central reservation width: 6 m
traffic interchanges: 5
overpasses: 6
bridges: 3

The project was implemented in two phases

Phase 1, completed in 2017: construction of the 2-lane road, overpasses, bridges and traffic interchanges.
Phase 2, completed in 2019: the road widening to comply with 1B category.

Approach Road to New Platov Airport Opened in Rostov-on-Don on 29th November 29.11.2017 Approach Road to New Platov Airport Opened in Rostov-on-Don on 29th November

A new 16 km four-lane road linked the airport with the northern by-pass of Rostov-on-Don and M-4 Don highway.

 
 

 